Skip to main content
Long Beach, CA
File #: 21-219WA    Version: 1 Name: Adopt Specifications WD-04-21 for the Sanitary Sewer Rehabilitation and Replacement Program (SSRRP) Project
Type: WA-Agenda Item Status: Approved
File created: 11/10/2021 In control: Water Commission (now under Utilities Commission)
On agenda: 11/18/2021 Final action: 11/18/2021
Title: Recommendation to adopt Specifications WD-04-21 for the Sanitary Sewer Rehabilitation and Replacement Program (SSRRP) Project No. 8 (SC-0402) and authorize the General Manager to sign a construction contract with Sancon Technologies, Inc. in the amount of $812,783. Bureau: Engineering
Attachments: 1. 2021 11-18 05 Sancon, 2. 2021 11-18 05 Sancon - Attachment, 3. 2021 11-18 04 & 05 Southwest & Sancon - Presentation

TITLE

Recommendation to adopt Specifications WD-04-21 for the Sanitary Sewer Rehabilitation and Replacement Program (SSRRP) Project No. 8 (SC-0402) and authorize the General Manager to sign a construction contract with Sancon Technologies, Inc. in the amount of $812,783.

 

Bureau:  Engineering

 

FISCAL IMPACT

The total FY 22 cost of the contract to the Sewer Fund will be $812,783.  The costs are included in the Sewer Fund FY 22 CIP budget and financial projections.

SUGGESTED ACTION

Approve recommendation.