Long Beach, CA
File #: 14-0477    Version: 1 Name: CM - Tidelands Beach Restroom - Bid Package 3 D3
Type: Contract Status: CCIS
File created: 5/19/2014 In control: City Council
On agenda: 7/1/2014 Final action: 7/1/2014
Title: Recommendation to authorize City Manager to amend Contract No. 33264 with NEI Contracting and Engineering, for an additional $80,489 for change order-related expenditures associated with the improvement of the Granada, Junipero and Mothers Beach South Restrooms (Tidelands Beach Restrooms - Bid Package 3); and execute all documents necessary to complete the construction of these beach restrooms, for a revised contract amount not to exceed $1,216,706. (District 3)
Sponsors: City Manager
Indexes: Amendments, Change Orders, Contracts
Attachments: 1. 070114-C-16sr.pdf
Related files: 13-0629
TITLE
Recommendation to authorize City Manager to amend Contract No. 33264 with NEI Contracting and Engineering, for an additional $80,489 for change order-related expenditures associated with the improvement of the Granada, Junipero and Mothers Beach South Restrooms (Tidelands Beach Restrooms - Bid Package 3); and execute all documents necessary to complete the construction of these beach restrooms, for a revised contract amount not to exceed $1,216,706. (District 3)

DISCUSSION
On July 23, 2013, the City Council authorized the City Manager to execute a contract with NEI Contracting and Engineering for an amount not to exceed $1,136,217 for the improvement of the Granada, Junipero and Mothers Beach South public restrooms. These restroom facilities were in significant disrepair and in dire need of renovation or reconstruction. While these restroom facilities were substantially completed and opened to the public in time for the Memorial Day weekend on May 24, 2014, additional contract authority is needed to close out the project and complete work associated with unforeseen conditions. The original cost estimate per location was:

i. $359,080 for Junipero (2630 E. Ocean Blvd)
ii. $415,010 for Granada (5098 E. Ocean Blvd)
iii. $362,127 for Mothers Beach South (5861 Appian Way)

In order to close out the project and complete all needed work, additional contract authority of $29,421 is needed for Junipero; $34,621 is needed for Granada: and $16,447 is needed for Mothers Beach South, to address unanticipated roof, dry rot, and termite emergency repairs at these restroom facilities and the adjacent concessions stand at Junipero and Granada.

Significant roof, dry rot and termite damage was discovered at the adjoining beach concessions stands, which share a roof and common walls with the beach restrooms. These unforeseen conditions must be at least minimally addressed to ensure public safety until permanent repairs are made. The overall condition of the beach conc...

Click here for full text