Title: Recommendation to adopt Plans and Specifications No. R-6767 and award an as-needed contract to All American Asphalt, for the annual contract for street improvements in an amount not to exceed $12,000,000; and authorize City Manager to execute any amendments thereto with All American Asphalt. (Citywide)
Sponsors: Public Works
Indexes: Contracts
Attachments: 1. 031009-R-21sr&att.pdf
Related files: 31065_001, 31065_000, 09-1329
TITLE
Recommendation to adopt Plans and Specifications No. R-6767 and award an as-needed contract to All American Asphalt, for the annual contract for street improvements in an amount not to exceed $12,000,000; and authorize City Manager to execute any amendments thereto with All American Asphalt. (Citywide)

DISCUSSION
This annual contract is available to a number of City Departments to provide for improvements to local and secondary streets and similar or related projects. The work includes street pavement, curbs and gutters, sidewalks, curb ramps, irrigation repairs and improvements, and taxiway repairs and improvements.

This is a procurement tool with no funds actually committed to the base contract. While Public Works will be responsible for the administrative control and monitoring of the contract, the contract is utilized by more than one department, and for various projects throughout the year, with no specific contract amount guaranteed to the contractor. The award amount for the annual contract is based on the following anticipated projects and funding:

PROJECTS/FUNDING AMOUNT

RDA Funds $4,500,000

Local Street Improvements
Proposition 1B $4,000,000

Major/Secondary Streets
Proposition C $5,000,000

Airport
Enterprise Fund $ 400,000

Public Service
Operating Budget $ 100,000

TOTAL $12,000,000


The specifications allow for an extension of the contract for up to two additional oneyear terms. In the event that a renewal option is exercised, the City will provide advance notification to the contractor and require any price increase to be submitted to the City Engineer for approval at least 60 days prior to expiration of the contract. The City reserves the right to accept or reject any price increase or to cancel the contract.