File #: 20-0792    Version: 1 Name: PRM - Master Fee & Charges Schedule & Public Seawall Mooring Leasing Permit D3
Type: Resolution Status: Adopted
File created: 8/4/2020 In control: City Council
On agenda: 8/18/2020 Final action: 8/18/2020
Title: Recommendation to authorize City Manager, or designee, to extend application of the Public Seawall Lease Program (Lease Program) to all phase areas of the Naples Permanent Seawall Repair Project (Project) in accordance with California Coastal Commission (CCC) Special Condition of Approval No. 10; and Adopt resolution amending the Master Fee and Charges Schedule and Public Seawall Lease Permit Fee (Fee) to $0.57 annual per square-foot in accordance with the Consumer Price Index (CPI) and making the Fee subject to future CPI adjustments on an annual basis using the fiscal year. (District 3)
Sponsors: Parks, Recreation and Marine
Attachments: 1. 081820-R-28sr&att.pdf, 2. RES-20-0101.pdf
Related files: P-00342_000, P-00347_000, P-00341_000, P-00348_000, P-00356_000, P-00349_000, P-00353_000, P-00376_000, P-00275_000, P-00276_000, P-00277_000, P-00293_000, P-00299_000, P-00302_000, P-00304_000, P-00305_000, P-00346_000, P-00350_000, 6P-00351_000, P-00352_000, P-00354_000, P-00355_000, P-00358_000, P-00359_000, P-00274_000, P-00278_000, P-00279_000, P-00284_000, P-00307_000, P-00310_000, P-00311_000, P-00312_000, P-00314_000, P-00316_000, P-00319_000, P-00320_000, P-00321_000, P-00322_000, P-00323_000, P-00324_000, P-00325_000, P-00326_000, P-00327_000, P-00328_000, P-00329_000, P-00331_000, P-00360_000, P-00363_000, P-00375_000, P-00381_000, P-00378_000, P-00379_000, P-00380_000, P-00382_000, P-00386_000, P-00400_000, P-00265_000, P-00266_000, P-00267_000, P-00268_000, P-00269_000, P-00270_000, P-00271_000, P-00272_000, P-00281_000, P-00285_000, P-00287_000, P-00288_000, P-00289_000, P-00290_000, P-00291_000, P-00292_000, P-00294_000, P-00295_000, P-00296_000, P-00297_000, P-00298_000, P-00300_000, P-00301_000, P-00303_000, P-00308_000, P-00309_000, P-00315_000, P-00317_000, P-00330_000, P-00332_000, P-00333_000, P-00334_000, P-00335_000, P-00336_000, P-00337_000, P-00338_000, P-00339_000, P-00340_000, P-00343_000, P-00344_000, P-00345_000, P-00357_000, P-00361_000, P-00362_000, P-00364_000, P-00365_000, P-00366_000, P-00367_000, P-00368_000, P-00369_000, P-00370_000, P-00371_000, P-00372_000, P-00374_000, P-00377_000, P-00383_000, P-00384_000, P-00387_000, P-00388_000, P-00389_000, P-00391_000, P-00399_000, P-00401_000, P-00402_000, P-00385_000, P-00392_000, P-00393_000, P-00394_000, P-00395_000, P-00396_000, P-00397_000, P-00398_000, P-00406_000, P-00407_000, P-00408_000
TITLE
Recommendation to authorize City Manager, or designee, to extend application of the Public Seawall Lease Program (Lease Program) to all phase areas of the Naples Permanent Seawall Repair Project (Project) in accordance with California Coastal Commission (CCC) Special Condition of Approval No. 10; and

Adopt resolution amending the Master Fee and Charges Schedule and Public Seawall Lease Permit Fee (Fee) to $0.57 annual per square-foot in accordance with the Consumer Price Index (CPI) and making the Fee subject to future CPI adjustments on an annual basis using the fiscal year. (District 3)

DISCUSSION
The 11,000-linear-foot Naples seawall system is divided into six prioritized phases (Attachments A and B), with Phase One addressing the area in the most imminent danger of collapse. The Phase One Project consisted of the repair of 1,915 linear feet of public seawalls located in the Rivo Alto Canal, from the Ravenna Bridge to the eastern portion of The Toledo Bridge. Phase One was completed on October 31, 2015.

On June 11, 2019, the City Council awarded a construction contract to Reyes Construction, Inc., to perform the Naples Island Permanent Seawall Repair, Phase Two of the project. The construction activities include the installation of 2,148 linear feet of new steel sheet-pile seawall on the water sides of the existing vertical seawalls at The Colonnade, the south side and eastern end of Treasure Island, and the western end of the Naples Peninsula. Additional scope includes new sidewalks, guardrails, storm drain systems, lighting, new float access platform supports and modifications, temporary storage/relocation of docks, and replacement of approximately 42 palm trees. Phase Two construction is expected to be completed in August/September 2020.

On October 9, 2013, the California Coastal Commission (CCC) approved the City’s application to proceed with the Project subject to 17 special conditions of approval, one of which required the City to institute a...