Long Beach, CA
File #: 08-0190    Version: 1 Name: PRM - Bixby Bandshell Roof
Type: Contract Status: CCIS
File created: 2/26/2008 In control: City Council
On agenda: 3/11/2008 Final action: 3/11/2008
Title: Recommendation to authorize City Manager to execute a first amendment to Agreement No. 30224 with CJ Tech Construction, Inc., for $85,371; extend the term through completion of repairs of the Bixby Park Band Shell; execute any future documents necessary to complete the reconstruction project; decrease appropriations in the Capital Projects Fund (CP) in the Department of Public Works (PW) by $11,916; and increase appropriations in the Capital Projects Fund (CP) in the Department of Parks, Recreation and Marine (PR) by $11,916. (District 2)
Sponsors: Parks, Recreation and Marine, Public Works
Indexes: Agreements, Amendments
Attachments: 1. 031108-C-11sr.pdf
Related files: 30224_000, 30224_001, 08-0316
TITLE
Recommendation to authorize City Manager to execute a first amendment to Agreement No. 30224 with CJ Tech Construction, Inc., for $85,371; extend the term through completion of repairs of the Bixby Park Band Shell; execute any future documents necessary to complete the reconstruction project; decrease appropriations in the Capital Projects Fund (CP) in the Department of Public Works (PW) by $11,916; and increase appropriations in the Capital Projects Fund (CP) in the Department of Parks, Recreation and Marine (PR) by $11,916.  (District 2)
 
DISCUSSION
 
On June 5, 2007, the City Council authorized the execution of Agreement No. 30224 with CJ Tech Construction, Inc., for the repair and remodel of the existing band shell structure in Bixby Park, in an amount not to exceed $179,000.
 
The project includes the following:
 
· Reconstruction of the northside wing to match the existing westside wing;
· Construction of a new trellis and support columns;
· Repair of the platform corner;
· Repair of the roof;
· Painting of all new and existing exterior woodwork;
· Stripping and painting of all existing decorative window metal grills.
 
Construction began September 10, 2007. In addition to two change orders, which exhausted contingency funds, the Department of Parks, Recreation and Marine has been requested to modify the project specifications to restore the historic appearance of the roof. Furthermore, the design for the electrical panel was incorrect and requires revision in order to meet Southern California Edison requirements. Implementation of these changes total $85,371.
 
A project shortfall of $11,916 will be funded using balances from completed projects within the Department of Public Works.
 
This matter was reviewed by Deputy City Attorney Gary J. Anderson on February 25, 2008, and Budget Management Officer Victoria Bell on February 25, 2008.
 
TIMING CONSIDERATIONS
City Council action is requested on March 11, 2008, in order to execute the first amendment to Agreement No. 30224 with CJ Tech Construction, Inc.
 
FISCAL IMPACT
In order to place all the necessary project funding in the same account, an appropriations decrease of $11,916 in the Capital Projects Fund (CP) in the Department of Public Works (PW), and an appropriations increase of $11,916 in the Capital Projects Fund (CP) in the Department of Parks, Recreation and Marine (PR) is requested. There is sufficient appropriation in the Capital Projects Fund (CP) in the Department of Parks, Recreation and Marine (PR) for the remaining portion of $85,371.
 
SUGGESTED ACTION
Approve recommendation.
 
BODY
[Enter Body Here]
 
Respectfully Submitted,
 
PHIL T. HESTER
DIRECTOR OF PARKS, RECREATION AND MARINE
 
 
MICHAEL P. CONWAY,
DIRECTOR OF PUBLIC WORKS
 
 
NAME
APPROVED:
TITLE
 
 
                                                  
 
PATRICK H. WEST
 
CITY MANAGER