Long Beach, CA
File #: 11-0479    Version: 1 Name: PW/PRM-Shoreline Marina Fuel Dock
Type: Contract Status: CCIS
File created: 4/26/2011 In control: City Council
On agenda: 5/17/2011 Final action: 5/17/2011
Title: Recommendation to authorize City Manager to execute all necessary documents to amend Contract No. 31822 with EFS West for design and construction of the Phase II portion of the Shoreline Marina Fuel Dock and Underground Storage Tank (UST) Improvement Project, increase the contract price by an estimated amount of $1,606,407, and execute all documents necessary for the implementation and administration of the Project; and Increase appropriations in the Marina Fund (TF 403) in the Department of Parks, Recreation and Marine (PRM), by $1,839,815 for construction and construction support costs related to this Project. (District 2)
Sponsors: Public Works, Parks, Recreation and Marine
Indexes: Amendments, Contracts
Attachments: 1. 051711-R-27sr.pdf
Related files: 10-0820, 31822_001, 12-0809
TITLE
Recommendation to authorize City Manager to execute all necessary documents to amend Contract No. 31822 with EFS West for design and construction of the Phase II portion of the Shoreline Marina Fuel Dock and Underground Storage Tank (UST) Improvement Project, increase the contract price by an estimated amount of $1,606,407, and execute all documents necessary for the implementation and administration of the Project; and

Increase appropriations in the Marina Fund (TF 403) in the Department of Parks, Recreation and Marine (PRM), by $1,839,815 for construction and construction support costs related to this Project. (District 2)

DISCUSSION
The City of Long Beach owns and operates three full-service marinas, including the Alamitos Bay Marina (Alamitos Bay), Long Beach Shoreline Marina (Shoreline Marina), and Rainbow Harbor/Rainbow Marina (Rainbow Marina), which are operated by the Parks, Recreation and Marine Department (PRM). To service these marinas, the City maintains two fueling docks, one in the Shoreline Marina and one in Alamitos Bay.

In September 2008, the Shoreline Marina fuel dock was closed as it did not meet current regulations. As a result, only the Alamitos Bay location is available for fueling needs. Recently, staff has been proceeding with the objective to remove and replace the UST and restore this facility to full operation. On August 3, 2010, City Council approved Contract No. 31822 with EFS West (Contractor) for Phase I of this project, which funded the removal of the existing non-compliant UST. Through this Council action, staff seeks to proceed with the replacement of the UST. Once these improvements are completed, the facility will be re-opened.

The contractor has completed the removal of the UST and has complied with all other environmental requirements related to UST removals in order to comply with the City's obligations and State regulations. The contractor is currently finalizing the remaining Phase I task of developing the pl...