Long Beach, CA
File #: 12-0869    Version: 1 Name: LBA/PW - Contruction of Taxiway D & A
Type: Contract Status: CCIS
File created: 9/21/2012 In control: City Council
On agenda: 10/9/2012 Final action: 10/9/2012
Title: Recommendation to adopt Plans and Specifications No. R-6900 for the Construction of improvements to Taxiway D North of Runway 7L-25R and Taxiway A West of Runway 12-30; award the project to and authorize City Manager to execute a contract with All American Asphalt the lowest responsible bidder, in an estimated amount of $2,997,000 plus a 25 percent contingency amount of $749,250, if necessary, and any necessary amendments thereto regarding term or scope of work; and increase appropriations in the Airport Enterprise Fund (EF 320) in the Airport Department (AP) by $2,759,142. (District 5)
Sponsors: Long Beach Airport, Public Works
Indexes: Contracts
Attachments: 1. 100912-R-10sr.pdf
Related files: 13-0930, 32880_000
TITLE
Recommendation to adopt Plans and Specifications No. R-6900 for the Construction of improvements to Taxiway D North of Runway 7L-25R and Taxiway A West of Runway 12-30; award the project to and authorize City Manager to execute a contract with All American Asphalt the lowest responsible bidder, in an estimated amount of $2,997,000 plus a 25 percent contingency amount of $749,250, if necessary, and any necessary amendments thereto regarding term or scope of work; and increase appropriations in the Airport Enterprise Fund (EF 320) in the Airport Department (AP) by $2,759,142. (District 5)

DISCUSSION
The asphalt concrete pavement on Taxiway D north of Runway 7L-25R, and Taxiway A west of Runway 12-30 is greatly deteriorated. The Pavement Condition Index (PCI) from the Airport’s Pavement Maintenance and Management System report completed in July 2011 ranges from 15-24 out of 100. Both Taxiways are in need of substantial work in order to improve the surface condition and extend the life of the pavement. The work on Taxiway D and Taxiway A will consist of the reconstruction of approximately 160,000 square feet of taxiway pavement. The work will also include improvements to the taxiway shoulders, pavement markings, drainage, infield grading, signage, and lighting systems. Runway guard lights will be installed at the Taxiway D intersections with Runway 12-30 and Runway 7L-25R as well as the Taxiway A intersection with Runway 12-30.

City Council adoption of the plans and specifications and award of the contract are being recommended concurrently to expedite implementation of this project. The project was advertised for bid June 11, 2012, and bids were opened July 25, 2012. In addition to placing an advertisement for bids in the Long Beach Press Telegram, notice of the bid was posted on the City’s website at www.PlanetBids.com/longbeach. In a continuing effort to increase participation of local businesses and Small Business Enterprises (SBEs), Minority Bu...

Click here for full text