Long Beach, CA
File #: 11-1112    Version: 1 Name: PW - Bay Shore Community Church parking lot
Type: Contract Status: CCIS
File created: 10/21/2011 In control: City Council
On agenda: 11/8/2011 Final action: 11/8/2011
Title: Recommendation to authorize City Manager to execute the First Amendment to Lease No. 30853 with Bay Shore Community Congregational Church for the shared use of the City-owned parking lot at the intersection of The Toledo and Livingston Drive. (District 3)
Sponsors: Public Works
Indexes: Amendments, Leases
Attachments: 1. 110811-C-16sr.pdf
Related files: 08-0789, 30853_001
TITLE
Recommendation to authorize City Manager to execute the First Amendment to Lease No. 30853 with Bay Shore Community Congregational Church for the shared use of the City-owned parking lot at the intersection of The Toledo and Livingston Drive. (District 3)

DISCUSSION
On August 19, 2008, the City Council authorized the execution of Lease No. 30853 (Lease) with Bay Shore Community Congregational Church (Bay Shore) for the shared use and improvement of the City-owned parking lot (Lot) at the intersection of The Toledo and Livingston Drive. The Lease provides Bay Shore with the exclusive use of the Lot weekly from noon on Saturdays to noon on Sundays, at a specified monthly rate. In addition, Bay Shore agreed to construct improvements (Project) to the Lot for the benefit of the greater community, under the agreement that the cost of the Project could be utilized to offset monthly rent for the Lot. The Lot is available, free of charge, to any member of the community on a first come, first serve basis, except for the time period rented by Bay Shore.

Although the Lease commenced September 2008, the Project was not fully completed until October 2009. The Project included repaving and striping of the parking lot, the addition of drought-tolerant landscaping and an associated irrigation system for both the Lot and adjoining parkways, the import of gravel for ground stabilization due to unknown soil conditions, and the widening of the adjacent alley and reconstruction of the curb to provide for safer access to the Lot and alley. The cost of the Project was originally estimated at between $75,000 and $100,000. The final cost was $113,306.

Under the terms of the Lease, the initial rent was identified as $300 per month with three percent annual increases. Bay Shore paid $4,200 in rent for an approximate 14-month period before the Project was completed and before the cost of the Project could be used to offset monthly rent. Based on the concept of a City a...

Click here for full text