Title: Recommendation to determine that the granting of Facility/Pipeline Permit Supplement No. S-2-11, under existing Facility/Pipeline Permit No. P-239-11 to The Boeing Company, will not be contrary to the public interest; and authorize City Manager to issue said permit supplement in accordance with Section 15.44.060, Permit Issuance, of the Long Beach Municipal Code. (District 5)
Sponsors: Public Works
Indexes: Permits
Attachments: 1. 071211-C-5sr&att.pdf
Related files: 11-0414, 11-0272
TITLE
Recommendation to determine that the granting of Facility/Pipeline Permit Supplement No. S-2-11, under existing Facility/Pipeline Permit No. P-239-11 to The Boeing Company, will not be contrary to the public interest; and authorize City Manager to issue said permit supplement in accordance with Section 15.44.060, Permit Issuance, of the Long Beach Municipal Code. (District 5)

DISCUSSION
The Boeing Company has filed an application for Facility/Pipeline Permit Supplement No. S-2-11, under existing Facility/Pipeline Permit No. P-239-11, to install seven lengths of piping across McGowen Street at two locations north of Cover Street. McGowen Street is located in the new Douglas Park development. See the attached vicinity map for the installation locations. The pipes range in size from two to six-inches in diameter and each length will be 68 feet long.

This installation will allow The Boeing Company to remediate area groundwater by extracting it through wells and delivering it through these proposed pipes to an off-site treatment system, where it will be treated and injected back into the subsurface through other wells. In addition to the extraction and injection of groundwater, the piping will house fiber optics for communications, wires for meter controls, and power to pumps and valves. Some piping will be spares for future use.

The Department of Public Works reviewed the application and found the proposed piping to be compatible with existing installations and not an obstacle to any street use or any known proposed developments. Traffic control requirements stipulated by the Traffic Engineering Division will be made a part of the special conditions for the excavation permit. Liability insurance and a bond for faithful performance will be processed following City Council authorization of the permit supplement. This project is categorically exempt, in accordance with Section 15301 of the California Environmental Quality Act.

This matter was rev...