File #: 22-1433    Version: 1 Name: LBA - Swinerton Builders for Phase II Terminal Area Improvements at LGB D45
Type: Contract Status: CCIS
File created: 11/14/2022 In control: City Council
On agenda: 12/6/2022 Final action: 12/6/2022
Title: Recommendation to authorize City Manager, or designee, to execute all documents necessary to amend Contract No. 34964 with Swinerton Builders, of Santa Ana, CA, for the construction of the Phase II Terminal Area Improvements at the Long Beach Airport, to increase the contract amount by $12,632,000, for a revised contract amount not to exceed $104,752,178, including contingencies; and Increase appropriations in the Airport Fund Group in the Airport Department by $12,632,000, offset by a combination of funds available for the Phase II Terminal Area Improvements Project at the Long Beach Airport. (Districts 4,5)
Sponsors: Long Beach Airport
Attachments: 1. 120622-R-48sr
Related files: 34964_009, 34964_010
TITLE
Recommendation to authorize City Manager, or designee, to execute all documents necessary to amend Contract No. 34964 with Swinerton Builders, of Santa Ana, CA, for the construction of the Phase II Terminal Area Improvements at the Long Beach Airport, to increase the contract amount by $12,632,000, for a revised contract amount not to exceed $104,752,178, including contingencies; and

Increase appropriations in the Airport Fund Group in the Airport Department by $12,632,000, offset by a combination of funds available for the Phase II Terminal Area Improvements Project at the Long Beach Airport. (Districts 4,5)

DISCUSSION
City Council approval is requested to amend Contract No. 34964 with Swinerton Builders to continue construction of the Phase II Terminal Area Improvements at the Long Beach Airport (Airport).

On May 8, 2018, the City Council awarded a design-build contract to Swinerton Builders (Swinerton) as part of its adoption of RFP AP18-033 for the design and construction of the Phase II Terminal Area Improvements (Phase II), in the amount of $58,809,490 plus a contingency of $6,450,000, for a total contract amount not to exceed $65,259,490. Focusing primarily on enhancing the pre-security customer experience and based on preliminary concept drawings and cost estimates, Phase II identified nine project components including a new ticketing lobby (Ticketing), new checked baggage screening facility (CBIS), new baggage claim facility (Baggage Claim), rehabilitation of the historic terminal (Terminal Renovation), relocation of rental car services into the historic terminal (Terminal Rental Car Counters), pre-security concessions, restrooms and enhancement of the meter/greeter plaza (Plaza Improvements), roadway improvements, rental car storage, and a ground transportation center.

Airport staff and Swinerton subsequently worked collaboratively with Airport stakeholders to finalize the design of Phase II. This included multiple design meetings identify...