TITLE
Recommendation to rescind the award of the contract to The SJ & B Group, Inc. for the Atherton Storm Drain between Hackett Avenue and Knoxville Avenue (Plans and Specifications No. R-6732); and authorize City Manager to award the contract to the second lowest bidder, Palp, Inc. dba Excel Paving, in an estimated amount of $1,229,431 plus a
25 percent contingency amount, if necessary. (District 4)
DISCUSSION
On February 12, 2008, the City Council awarded the above referenced contract to the lowest bidder, The SJ & B Group, Inc. (Contractor), in the amount of $1,183,350. Subsequently, the Contractor has failed to fully execute the contract and provide the associated bonds and insurance in order to proceed with the construction of the project. In addition, the Contractor has informed the City they will not be able to perform under the contract. As a result, the City is recommending that the award be rescinded and that the contract be awarded to the next lowest bidder. In addition, the City will declare the bid security to be forfeited, and the bond for the bid security in the amount of $46,081 (the difference between the lowest and second bidders) will be deposited into the City Treasury.
This matter was reviewed by Principal Deputy City Attorney Charles Parkin on March 24, 2008 and by Budget Management Officer Victoria Bell on March 24, 2008.
TIMING CONSIDERATIONS
City Council action on this matter is requested on April 1, 2008 to authorize commencement of this Public Works project. Construction is projected to begin in May 2008 and should take approximately 120 working days.
FISCAL IMPACT
The contract award to the second lowest bidder is for an estimated amount of $1,229,431 plus a 25 percent contingency amount of $307,357, if necessary. This amount is $46,081 greater than the original award, but will be recovered through the forfeiture of the bid bond of the original low bidder, The SJ & B Group Inc. Sufficient funds to cover the contract are b...
Click here for full text