File #: 18-0372    Version: 1 Name: LBA - Completion of Revovation of Lot A Parking Garage D5
Type: Contract Status: CCIS
File created: 4/12/2018 In control: City Council
On agenda: 5/1/2018 Final action: 5/1/2018
Title: Recommendation to authorize City Manager, or designee, to execute all documents necessary to amend Contract No. 34403 with R.J. Daum Construction Company, of Garden Grove, CA, to increase the contract amount by $26,149, for a total amount not to exceed $4,942,373, for the completion of capital improvements to the Long Beach Airport’s Parking Structure A. (District 5)
Sponsors: Long Beach Airport
Attachments: 1. 050118-C-13sr.pdf
Related files: 34403_002
TITLE
Recommendation to authorize City Manager, or designee, to execute all documents necessary to amend Contract No. 34403 with R.J. Daum Construction Company, of Garden Grove, CA, to increase the contract amount by $26,149, for a total amount not to exceed $4,942,373, for the completion of capital improvements to the Long Beach Airport’s Parking Structure A. (District 5)

DISCUSSION
On August 9, 2016, the City Council awarded Contract No. 34403 to R.J. Daum Construction Company (RJD), for capital improvements to Parking Structure A at the Long Beach Airport (Airport), in the amount of $3,932,979 and authorized a 25 percent contingency ($983,245), for a total contract amount not to exceed $4,916,224. The capital improvements included the demolition of the existing elevator and staircase tower and the construction of a new two-cab elevator tower and an outdoor staircase at the northwest corner of the structure.

During construction, the Airport identified additional work to enhance the efficiency, safety, and aesthetics of the structure. The additional work included implementation of new passenger wayfinding signage, repainting of the entire parking structure, and interior and exterior asphalt pavement rehabilitation. To avoid future closures of Structure A, which would pose significant operational challenges, the Airport requested RJD to perform these additional tasks during the performance of the contract items. The improvements have been fully implemented, and construction has been completed.

Initially, it was anticipated there would be sufficient funding under the initial contract authorization to complete additional work. During project final reconciliation, it was determined that the additional tasks requested by the Airport required 24 working days above the contract time to complete, including an unanticipated cost of additional supervisory staff time, along with other related items. The total construction cost of the project is $4,942,373, wh...