File #: 18-0074    Version: 1 Name: CD3-Traffic Safety Fencing
Type: Agenda Item Status: Approved
File created: 1/19/2018 In control: City Council
On agenda: 1/23/2018 Final action: 1/23/2018
Title: Recommendation to approve the use of the Third Council District's one-time infrastructure funds in the Capital Projects Fund (CP) in the Public Works Department (PW) in the amount of $10,000 to support the installation of traffic safety fencing at Bellflower Boulevard and 7th Street.
Sponsors: COUNCILWOMAN SUZIE A. PRICE, THIRD DISTRICT
Attachments: 1. 012318-NB-22sr&att.pdf

TITLE

Recommendation to approve the use of the Third Council District's one-time infrastructure funds in the Capital Projects Fund (CP) in the Public Works Department (PW) in the amount of $10,000 to support the installation of traffic safety fencing at Bellflower Boulevard and 7th Street.

 

DISCUSSION

With concerns around safety at the intersection of Bellflower Boulevard and 7th Street, additional fencing is needed to reduce pedestrian access to medians on Bellflower Boulevard, south of 7th Street, and on 7th Street, east of Bellflower Boulevard.

 

FISCAL IMPACT

The total project cost of $10,000 is funded by the Third Council District's one-time infrastructure funds in the Capital Projects Fund (CP) in the Public Works Department (PW).

 

SUGGESTED ACTION

Approve recommendation.

 

Respectfully Submitted,

SUZIE PRICE

COUNCILWOMAN, THIRD DISTRICT