File #: 06-0208    Version: 1 Name: PW - Execute first amendment with August Construction, Inc.
Type: Contract Status: CCIS
File created: 3/8/2006 In control: City Council
On agenda: 3/14/2006 Final action: 3/14/2006
Title: Recommendation to authorize City Manager to execute the First Amendment to Contract No. 29456 with August Construction, Inc., for the Improvement of Naples Island Soil Anchors, Phase V, in an amount not to exceed $461,857, for a total contract amount of $1,094,086, plus a 25 percent contingency amount of $273,522, if necessary; and Increase appropriations in the Tidelands Capital Fund (TF) and the Department of Public Works (PW) by $577,321. (District 3)
Sponsors: Public Works
Indexes: Contracts
Attachments: 1. C-20sr, 2. C-20att
Related files: 05-3377, 29456_001
TITLE
Recommendation to authorize City Manager to execute the First Amendment to Contract No. 29456 with August Construction, Inc., for the Improvement of Naples Island Soil Anchors, Phase V, in an amount not to exceed $461,857, for a total contract amount of $1,094,086, plus a 25 percent contingency amount of $273,522, if necessary; and
 
Increase appropriations in the Tidelands Capital Fund (TF) and the Department of Public Works (PW) by $577,321.  (District 3)
 
DISCUSSION
On November 1, 2005, the City Council authorized the City Manager to execute a contract with August Construction, Inc., in an amount not to exceed $632,229. Due to an increase in the amount of Tidelands funds available, staff recommends an increase in current appropriations to install  additional soil anchors at various locations (see attached vicinity map). The contractor, August Construction, Inc., is willing and ready to perform the necessary additional soil anchor installations.
 
A first amendment to Contract No. 29456 with August Construction, Inc., in the amount of $461,857, is needed to perform the additional soil anchor installations. These soil anchors will replace the existing tie-rods and stabilize the adjoining property. This project has been coordinated with the Naples Island Association.
 
The original Council approval included a contingency of up to 25 percent above the award amount. With the new contract amount of $1,094,086, the new contingency amount is $273,522, if needed.
 
This matter was reviewed by Senior Deputy City Attorney Donna F. Gwin on February 16,2006, and Budget Management Officer David Wodynski on March 1 , 2006.
 
 
TIMING CONSIDERATIONS
City Council action on this matter is requested on March 14, 2006, to ensure that there are no construction delays.
 
 
FISCAL IMPACT
The recommended amendment to August Construction, Inc.'s, contract will increase it by $461,857 for a total contract amount of $1,094,086, plus a 25 percent contingency amount of $273,522, if necessary. An appropriation increase in the amount of $577,321 will be required to provide sufficient funds to cover the contract amendment in the Tidelands Operations Fund (TF) in the Department of Public Works (PW) and is included in the recommended actions.
 
 
SUGGESTED ACTION
Approve recommendation.
 
Respectfully Submitted,
 
 
 
CHRISTINE F. ANDERSEN
APPROVED:
DIRECTOR OF PUBLIC WORKS
 
 
                                                  
 
GERALD R. MILLER
 
CITY MANGER